The Town of Farragut and the Tennessee
Department of Transportation (TDOT) are improving the intersection
of Kingston Pike and Watt Road. Now that the South Watt Road
extension is complete, a southbound right turn lane will be added
to North Watt Road. A new sidewalk and crosswalk will also be built
along the southbound lane. Once complete, there will be a pedestrian
connection from Old Stage Road to Mayor Bob Leonard Park.
Project Designer:
Qk4, Inc.
Construction Contractor:
J&M Grading
Current Contract Amount:
$1,396,799.20
Project Schedule:
Bid Letting: March 2021 Notice to Proceed:Summer 2021 Contract Completion Date: Summer 2022
Contact:
Engineering Department (865) 966-7057
Status:
Construction on-going, completion remains forecast for early Summer of 2022.