McFee Park Phase 3

A photo of the undeveloped area at McFee Park

​Background:

McFee Park is a 51+ acre site with approximately 35 acres left for future development. Phase 1 construction included a restroom/storage building, entrance drive, lighted parking, lighted rectangular and practice fields and a walking trail. Phase 2 construction included a splash pad, lighted playground, two large pavilions, lighted parking, restroom/storage building and additional walking trails. The original splashpad was replaced and enlarged in 2015. 

Project Description:

Phase 3 will include mass grading of the site; road connection from the current road to a new entrance on McFee Road; site utility systems (water, sewer and underground electric) for the entire project including stubouts for work in future phases; stormwater systems for project including stubouts for work in future phases; four lighted tennis/pickleball courts, one full size basketball court with a tennis hitting wall, restroom/small pavilion; tennis complex parking lot and associate parking lot lighting; great lawn; and the walking trail loop around the great lawn along with associated lighting. 

Phase 3 Site Plan
Master Plan Survey Results - Fall 2016
Master Plan Public Comments - Fall 2016 

Project schedule:

(tentative) 
  • Design: In process
  • Bidding: Winter 2020
  • Construction: Spring 2021-Spring 2022

Project Designer:

Ross/Fowler, LLC

Project Budget:

 
  • Master Plan: $39,500
  • Design Process: $659,000
  • Construction: $8,000,000

Construction Contractor

: TBD